Microsoft Project XML files
Tasks can be imported from Microsoft Project XML files.
-
Create an MS project with the following columns:
- Unique ID
- ID
- Task Name
- Start
- Finish
- Cost
- If you want the MS project linked to the right groups, you must add the column VdcGroup and specify model groups.
- Note: Use / to create subgroups.
- After creating the columns, export the project to an XML file.

Importing XML
Import the XML file to Scheduler via Schedule > Import.

Additional columns
MAGNET Explorer can import Excel files to add additional columns to 5D tasks.
- Format column names similar to those shown (example: column for CO2 emissions during construction).
- Select the type of data that needs to be imported in the Export Wizard - Map Options screen.

In the Export Wizard - Task Mapping screen, add these items:
- Unique ID
- ID
- Name
After exporting, edit the column name Unique_ID to Unique ID.
Note: The Excel sheet should be named 6D Attributes.

Now you can import the Excel file to Scheduler.