  • First, copy the GC3 control file for the jobsite to a USB drive. 
  • Insert that USB drive into the GT instrument.
  • With the LPS_Setup program running on the GT, tap on the Setup File button.
  • With the USB drive inserted in the GT, you should see two Location options in this screen.
    • Internal memory: Internal storage on the GT
    • (USB) Removable Disk: USB drive inserted into the GT
  • To copy the GC3 file from the USB drive, hit the Copy... button
  • The idea is to copy from the USB drive into the internal memory. 
  • Set the From/To options like the example to the right.
  • You should now see the file name of the GC3 file on the USB drive. 
  • Tap on it and hit OK.
  • A message should now appear indicating that the GC3 file will be set as the current project.
  • Hit Yes to continue.
  • You should now be back at the main LPS_Setup menu.
  • At the top of the screen, there should now be a file name indicating the currently active GC3 file.