This article summarizes what is new in MAGNET Project module v6.0, discussing the main differences between version 5.1.1 and version 6.0.

Log in or sign up for myTopcon to view this page:

MAGNET Project: Differences between versions

Make planning easier and more flexible

Version 6 is a rewrite of the previous version of MAGNET Project software. The aim is to make planning easier and more flexible. This version will support a wider usage and easier scheduling of non-earthwork tasks as before. It will also make future development faster and more agile.

  • MAGNET Project continues to be a tool for mass optimization, scheduled mass haul planning, visual project planning, and production follow-up.
  • The changes make the program easier-to-use for new users, as well as providing more flexibility and opportunities for experienced users.
  • There is a new user interface with new features, filters, and views.
  • MAGNET Project 6 supports planning at different levels of detail. It will be easier to get started in a phase where you do not have all the information. You can add more details to the plans later.
  • Version 6 doesn’t require Excel being installed on the computer anymore.
  • It will support the new MAGNET licensing system that allows users to choose from available serial numbers in the license pool.
  • It is easier to make a scheduled mass haul plan, resulting in time savings and achieving the desired results faster.
  • There is a new way to visualize results better.

Removed functionalities

Features dropped from v6.0 that were available in v5.1 include the following:

  • Export to Primavera P6 XML format
  • Support for some language translations
  • Importing actual haul data from Sitelink3D Haul Truck system
  • Manual creation of hauls
  • Forecast progress based on actuals in Time-location view
  • Mass curve view
  • Resource view
  • Control view 
  • Export tasks as DynaRoad XML (old format)
  • Import quantities from DynaRoad XML (old format)
  • Send resource graph to iSeekPlant
  • Import alignment coordinates from VGP files (old Trimble Tekla Xroad/Xstreet format)
  • Type-derived dependencies
  • Identified resources (machine license plate)
  • Resource number limitations
  • Print to PDF directly from the program (In v6, you can print to a separate PDF printer.)

New and improved features

New features in v6.0 include:

  • Flexible scheduling where tasks' attributes are optional (Tasks aren’t required to have quantities, locations, resources, and production rates anymore.)
  • Export to Microsoft Project 2013 XML format
  • Import from Microsoft Project 2013 XML format
  • Possibility to add metadata columns to tasks
  • Support for WMS background maps
  • Flexible text reports that a user can define and modify
  • Possibility to save location layouts (view settings)
  • Possibility to import actual quantities from Excel or MAGNET Office
  • Improved possibilities to add text boxes, images, and graphics in views
  • Autosave backup file
  • Possibility to use multiple monitor setup and look at views on different monitors
  • Project quantities are imported and stored in full accuracy
  • V6.0 haul calculation is based on distance, unless you define haul resource costs (In v5.1, haul calculation was based on a haul cost table.)
  • New *.mjp file format
    • MAGNET Project 6.0 can open files saved with the latest DynaRoad version v5.6.3 or with MAGNET Project v5.1. If a user has older files, they should be opened with the latest v5.1 version and resaved before updating to v6.0.